10 Freeway Drainage Installation To 405 Freeway Ramp Starts Today For Five Weeks:

The 405 Sepulveda Pass Improvements Project enters a new stage with the contractor continuing drainage installation along the eastbound I-10 to southbound I-405 connector ramp starting today, Nov. 2 for about five weeks.

Work will also be located along the west side of southbound I-405, just south of the I-10 interchange. Night time work is required due to the need for the connector ramp closure.

In other related news, the contractor begin relocating a telecommunication line on the property of the General Services Administration (GSA) between Sepulveda and Veteran. The work starts today, Nov. 1, 2011 for about two months.

Work activities will take place during day and night time hours.

Day time hours start at 8 a.m. until 5 p.m. and will not require lane reductions.

Night activities, from 8 p.m. to 5 a.m., will require lane reductions through the GSA driveway from Sepulveda to Veteran for several nights.

One lane will remain open for two directions of traffic, with a flagger being used to direct traffic.Some sections of GSA parking will be restricted during this time.

Previous Article

‘Health, Wellness and Pursuit of Happiness’ SMC Juried Student Show Starts Saturday:

Next Article

Pacific Park To Host Special Birthday Party On 11-11-11:

You might be interested in …

LAPD

Silver Alert issued for Missing South LA Woman

Gail Sanders was reported missing from the 1800 block of West 48th Street around 6:45 p.m. on June 2. Authorities and family are searching for a 74-year-old woman with dementia who was last seen Tuesday […]